January 24, 2018

2018 Tulloch Spring Fill

The Spring 2018 Tulloch fill schedule will be done in two phases. The first phase will take place between February 1 and March 12, when the reservoir pool will be raised back to the normal winter elevation of 501.6 ft. The rate of fill will approximately follow the daily ranges below, but there may be substantial variations due to natural inflow or storm events. Since this phase of the reservoir fill is not governed by USACE flood control requirements, any extra inflow will be retained rather than released.

The second phase of the reservoir fill will follow the typical spring fill procedures, which follow the USACE flood control curve upward. During this phase, the reservoir will be managed to the given target elevation ranges as much as possible. Some variations may still occur due to large natural inflows or facility and operational constraints.

2018 Tulloch Spring Fill

Phase 1: Elevation targets are approximate.

DateLowHigh
1/31/2018475.0478.0
2/1/2018475.6478.6
2/2/2018476.2479.2
2/3/2018476.8479.8
2/4/2018477.4480.4
2/5/2018478.0481.0
2/6/2018478.5481.5
2/7/2018479.1482.1
2/8/2018479.7482.7
2/9/2018480.3483.3
2/10/2018480.9483.9
2/11/2018481.5484.5
2/12/2018482.1485.1
2/13/2018482.7485.7
2/14/2018483.3486.3
2/15/2018483.9486.9
2/16/2018484.4487.4
2/17/2018485.0488.0
2/18/2018485.6488.6
2/19/2018486.2489.2
2/20/2018486.8489.8
2/21/2018487.4490.4
2/22/2018488.0491.0
2/23/2018488.6491.6
2/24/2018489.2492.2
2/25/2018489.8492.8
2/26/2018490.3493.3
2/27/2018490.9493.9
2/28/2018491.5494.5
3/1/2018492.1495.1
3/2/2018492.7495.7
3/3/2018493.3496.3
3/4/2018493.9496.9
3/5/2018494.5497.5
3/6/2018495.1498.1
3/7/2018495.7498.7
3/8/2018496.2499.2
3/9/2018496.8499.8
3/10/2018497.4500.4
3/11/2018498.0501.0
3/12/2018498.3501.3

Phase 2:

FromThroughLowHigh
3/13/20183/19/2018498.6501.6
3/20/20183/26/2018499.4502.4
3/27/20184/02/2018500.1503.1
4/03/20184/09/2018500.9503.9
4/10/20184/16/2018501.7504.7
4/17/20184/23/2018502.4505.4
4/24/20184/30/2018503.2506.2
5/01/20185/08/2018504.0507.0
5/09/20185/15/2018505.5508.5
5/16/20185/23/2018506.5509.5
5/24/20189/15/2018506.5509.3

 

Article by Tri-Dam Project / Fill Schedule, Tulloch Reservoir

News & Updates

Tulloch Spring 2023 Fill Schedule

March 24, 2023 by Tri-Dam Project

Tulloch Winter 2022/2023 Drawdown Schedule

September 8, 2022 by Tri-Dam Project

Road Conditions

Current road conditions to Beardsley and Donnells Reservoirs can be found on their respective pages.