July 29, 2020

Tulloch Winter 2020/2021 Drawdown Schedule

Updated: 9/28/20

State regulations for the cycling and inspection of gates at the dam have changed from every five years to every three years. In our effort to be fully compliant and ensure the utmost safety of our facilities, Tri-Dam will transition to a three year schedule this winter. The drawdown schedule has been coordinated with the United States Bureau of Reclamation (USBR), and will be implemented as shown. The schedule follows the general pattern used in past extraordinary drawdown years. Please note that once the reservoir is down to 475’ by January 3, 2021 , it will remain at that level until January 9, 2021 to provide time for Tri-Dam to conduct the required inspections with State and Federal officials. After that occurs, USBR will slowly begin the fill schedule. An additional schedule will be produced by the USBR, and that will be distributed by Tri-Dam immediately upon receipt.

As always, the published schedule is subject to change in the event of weather events and other operational factors, thus we encourage all persons to exercise caution when operating in an around the reservoir.

DateElevation LowElevation High
9/30/2020505.9508.9
10/4/2020503.9506.9
10/7/2020502.0505.0
10/10/2020500.0503.0
10/14/2020498.0501.0
10/21/2020496.0499.0
10/28/2020494.0497.0
11/1/2020492.9495.9
11/2/2020492.6495.6
11/3/2020492.3495.3
11/4/2020492.0495.0
11/5/2020491.7494.7
11/6/2020491.5494.5
11/7/2020491.2494.2
11/8/2020490.9493.9
11/9/2020490.6493.6
11/10/2020490.3493.3
11/11/2020490.0493.0
11/12/2020489.8492.8
11/13/2020489.5492.5
11/14/2020489.2492.2
11/15/2020488.9491.9
11/16/2020488.6491.6
11/17/2020488.3491.3
11/18/2020488.1491.1
11/19/2020487.8490.8
11/20/2020487.5490.5
11/21/2020487.2490.2
11/22/2020486.9489.9
11/23/2020486.6489.6
11/24/2020486.4489.4
11/25/2020486.1489.1
11/26/2020485.8488.8
11/27/2020485.5488.5
11/28/2020485.2488.2
11/29/2020484.9487.9
11/30/2020484.6487.6
12/1/2020484.4487.4
12/2/2020484.1487.1
12/3/2020483.8486.8
12/4/2020483.5486.5
12/5/2020483.2486.2
12/6/2020482.9485.9
12/7/2020482.7485.7
12/8/2020482.4485.4
12/9/2020482.1485.1
12/10/2020481.8484.8
12/11/2020481.5484.5
12/12/2020481.2484.2
12/13/2020481.0484.0
12/14/2020480.7483.7
12/15/2020480.4483.4
12/16/2020480.1483.1
12/17/2020479.8482.8
12/18/2020479.5482.5
12/19/2020479.3482.3
12/20/2020479.0482.0
12/21/2020478.7481.7
12/22/2020478.4481.4
12/23/2020478.1481.1
12/24/2020477.8480.8
12/25/2020477.6480.6
12/26/2020477.3480.3
12/27/2020477.0480.0
12/28/2020476.7479.7
12/29/2020476.4479.4
12/30/2020476.1479.1
12/31/2020475.9478.9
1/1/2021475.6478.6
1/2/2021475.3478.3
1/3/2021475.0478.0
1/4/2021475.0478.0
1/5/2021475.0478.0
1/6/2021475.0478.0
1/7/2021475.0478.0
1/8/2021475.0478.0
1/9/2021475.0478.0
1/10/2021475.0478.0
1/11/2021475.6478.6
1/12/2021476.2479.2
1/13/2021476.8479.8
1/14/2021477.4480.4
1/15/2021478.0481.0
1/16/2021478.6481.6
1/17/2021479.2482.2
1/18/2021479.8482.8
1/19/2021480.4483.4
1/20/2021481.0484.0
1/21/2021481.6484.6
1/22/2021482.2485.2
1/23/2021482.8485.8
1/24/2021483.4486.4
1/25/2021484.0487.0
1/26/2021484.6487.6
1/27/2021485.2488.2
1/28/2021485.8488.8
1/29/2021486.4489.4
1/30/2021487.0490.0
1/31/2021487.6490.6
2/1/2021488.2491.2
2/2/2021488.8491.8
2/3/2021489.4492.4
2/4/2021490.0493.0
2/5/2021490.6493.6
2/6/2021491.2494.2
2/7/2021491.8494.8
2/8/2021492.4495.4
2/9/2021493.0496.0
2/10/2021493.6496.6
2/11/2021494.2497.2
2/12/2021494.8497.8
2/13/2021495.4498.4
2/14/2021496.0499.0
2/15/2021496.6499.6
2/16/2021497.2500.2
2/17/2021497.8500.8
2/18/2021498.4501.4
2/19/2021498.6501.6
3/22/2021498.6501.6

 

Article by Tri-Dam Project / Fill Schedule, Tulloch Reservoir

March 16, 2020

Tulloch Spring 2020 Fill Schedule

From: Bureau of Reclamation

2020 Tulloch Spring Fill will follow the typical spring fill procedures, which follow the USACE flood control curve upward. During the spring fill, the reservoir will be managed to the given target elevation ranges as much as possible. Some variations may still occur due to large natural inflows or facility and operational constraints.

Date
From
Date
Through
Elevation
Low
Elevation
High
3/16/20203/22/2020498.6501.6
3/23/20203/29/2020499.4502.4
3/30/20204/05/2020500.1503.1
4/06/20204/12/2020500.9503.9
4/13/20204/19/2020501.7504.7
4/20/20204/26/2020502.4505.4
4/27/20205/03/2020503.2506.2
5/04/20205/10/2020504.0507.0
5/11/20205/17/2020505.5508.5
5/18/20205/24/2020506.5509.5
5/25/20209/15/2020506.5509.5

Issued by: T. Washburn

Article by Tri-Dam Project / Fill Schedule, Tulloch Reservoir

September 6, 2019

Tulloch Fall 2019 Drawdown Schedule

The fall drawdown schedule for Tulloch Reservoir is provided below. This schedule complies with U.S. Army Corps of Engineers flood control requirements. The reservoir will generally be managed to the target elevation range, however some variation may occur due to large local inflow during rain events or facility and operational constraints.

Date
From
Date
Through
Elevation
Low
Elevation
High
9/16/20199/22/2019506.0509.0
9/23/20199/29/2019504.7507.7
9/30/201910/06/2019503.5506.5
10/07/201910/13/2019502.2505.2
10/14/201910/20/2019500.9503.9
10/21/201910/27/2019499.5502.5
10/28/201903/22/2019498.6501.6

For further information, please see the Tulloch Reservior page.

Issued by: T. Washburn

Article by Tri-Dam Project / Fill Schedule, Tulloch Reservoir

March 25, 2019

Tulloch Spring 2019 Fill Schedule

Below is the 2019 Tulloch fill schedule, as just received from the Bureau of Reclamation. As always, the schedule is subject to substantial variation due to natural inflow during or after storm events. Please exercise caution when operating in and around the reservoir at all times.

2019 Tulloch Spring fill will follow the typical spring fill procedures, which follow the USACE flood control curve upward. During the spring fill, the reservoir will be managed to the given target elevation ranges as much as possible. Some variations may still occur due to large natural inflows or facility and operational constraints.

Date
From
Date
Through
Elevation
Low
Elevation
High
3/22/20193/31/2019498.6501.6
4/01/20194/07/2019499.4502.4
4/08/20194/14/2019500.1503.1
4/15/20194/21/2019500.9503.9
4/22/20194/28/2019501.7504.7
4/29/20195/05/2019502.4505.4
5/06/20195/12/2019503.2506.2
5/13/20195/19/2019504.0507.0
5/20/20195/26/2019505.5508.5
5/27/20196/02/2019506.5509.5
6/03/20199/15/2019506.5509.5

Issued by: T. Washburn

Article by Tri-Dam Project / Fill Schedule, Tulloch Reservoir

September 6, 2018

Tulloch Fall 2018 Drawdown Schedule

The fall drawdown schedule for Tulloch Reservoir is provided below. This schedule complies with U.S. Army Corps of Engineers flood control requirements. The reservoir will generally be managed to the target elevation range, however some variation may occur due to large local inflow during rain events or facility and operational constraints.

Date
From
Date
Through
Elevation
Low
Elevation
High
9/17/20189/23/2018506.0509.0
9/24/20189/30/2018504.7507.7
10/01/201810/07/2018503.5506.5
10/08/201810/14/2018502.2505.2
10/15/201810/21/2018500.9503.9
10/22/201810/28/2018499.5502.5
10/29/201803/22/2019498.6501.6

 

Article by Tri-Dam Project / Fill Schedule, Tulloch Reservoir

  • « Previous Page
  • 1
  • 2
  • 3
  • 4
  • Next Page »

News & Updates

Tulloch Spring 2023 Fill Schedule

March 24, 2023 by Tri-Dam Project

Tulloch Winter 2022/2023 Drawdown Schedule

September 8, 2022 by Tri-Dam Project

Road Conditions

Current road conditions to Beardsley and Donnells Reservoirs can be found on their respective pages.

Copyright © 2007–2023 Tri-Dam Project · Website by Webdancers · Employee Log in · Website Log in
PO Box 1158 · Pinecrest, CA 95364-0158 · 209-965-3996